Getting power connected to a new rural block
Bought a block on the Dorrigo Plateau or in the Bellinger valley? The steps to get power on, who does what, and what to sort out before you build.
You have bought the block. Now you need power. On a rural block this takes longer than people expect, so start early.
Who does what
- The network. The poles and wires up here belong to Essential Energy. Anything on their side needs their approval.
- Your electrician. Your side: the meter box, the main switchboard, and everything from there into the house and sheds.
- Your power company. The retailer you pay the bill to arranges the meter.
Sort these out early
- How far is the nearest power? A pole at the front gate is simple. A pole a kilometre away is a much bigger job.
- Where will the house and sheds go? That decides where the meter box goes and how long the cable runs are.
- What will you run? A weekender is not the same as a house, a workshop and an EV charger.
- Temporary power. Your builder will want power on site before the house exists.
Talk to an electrician before the slab goes down
Planning it right is far cheaper than changing it later. Michael does new supplies, meter boxes and new build wiring, and will tell you which parts are his and who else needs to be involved.
Common questions
Who owns the power lines on the Dorrigo Plateau?
The network in this area is Essential Energy.
Do you install meter boxes?
Yes. New supplies and meter boxes are part of the rural work Michael does.
When should I call the electrician on a new build?
Before the slab or footings go in, so the meter box, switchboard and cable runs are planned around the house.
More guides
- Getting power to a shed, pump or workshop on a rural property
- Test and tag for farms, workplaces and building sites
- Power out at your place? Your problem or the network?
- Electrician in Dorrigo: how to get a job sorted
Wright Electrical & Communications · Licensed electrician on the Dorrigo Plateau · 0401 016 491 · All guides